Welbeck Health Partners: Step 0B Project

A small refurbishment project for a private health care centre. To maintain the operation of the medical centre, the project had to be carried out outside of normal working hours. Works consisted of three phases as following;

  1. Refurbish existing dirty laundry room and fit-out for a Standing CT Scanning facility.

  2. Strip out to existing Standing CT Scanning facility and reduce the overall width of adjacent existing services riser to enable fortune expansion plans. This involved alterations to live services and the reconstruction of riser’s shaft-walls in accordance with British Gypsum’s White Book, as well as making good to existing finishes and the application of new finishes as required.

  3. Removal of existing main entrance revolving doors, and the installation of new automated sliding doors including all associated life safety systems interface and security access control along with CCTV system upgrade.

 The project’ programme was for the duration of 22 weeks including design and manufacturing of new sliding doors, whilst construction duration on site lasted for 8 weeks in total for all 3 phases.